Roadwork for the week of Dec. 19
/cloudfront-us-east-1.images.arcpublishing.com/gray/3L2IOUKE4FACBNSZY5LDZWSULU.png)
EAST TEXAS (KLTV/KTRE) - TxDOT is planning to conduct the following construction and maintenance work in the district during the week of Dec. 19, 2022. Work schedules are subject to change due to weather conditions, equipment failure, or other unforeseen issues. Slow down and pay attention in work zones.
Anderson County
Palestine crews will be edging on various roadways throughout the county. Expect lane closures with flaggers and a pilot car controlling traffic.
Anderson County construction projects updates:
SH 175 Widening Project
- Limits: From 0.4 miles SE of SH 155, SE to Cuney
- Contractor: Big Creek Construction, LTD
- Cost: $55.5 million
- Anticipated Completion Date: Spring 2026
The contractor is scheduled to work on the new eastbound bridge and roadway elements. The speed limit is reduced throughout the project limits. Motorists should use caution when traveling through the project and expect lane closures and delays. Project consists of expansion to a four-lane roadway with new bridges across the Neches River.
SH 155 Overlay Project
- Limits: From 0.14 Mi S of FM 19 (End of Curb and Gutter) to S of FM 315
- Contractor: Madden Contracting Company, LLC
- Cost: $14.6 million
- Anticipated Completion Date: Summer 2023
The contractor is scheduled to work on the guardrail. The speed limit is scheduled to be reduced to 60 mph throughout the project limits. Motorists should use caution when traveling through the project and expect lane closures and delays. It consists of OCST, PFC surface, shoulder texturing, edge treatment and pavement markings.
Flashing Chevrons Safety Project
- Limits: FM 321, etc.
- Contractor: Marcom’s Mowing Service, LLC.
- Cost: $0.8 million
- Anticipated Completion Date: Winter 2022
The contractor is scheduled to continue installing signs at various locations throughout Anderson and Henderson County. Motorists should use caution when traveling through the project and expect lane closures and delays. Project consists of installing chevrons and advance warning signals.
District Mill and Inlay Project
- Limits: US 287, etc.
- Contractor: Big Creek Construction, LTD
- Cost: $0.8 million
- Anticipated Completion Date: Winter 2022
The contractor is scheduled to work on roadway elements in various locations in Anderson County. Motorists should use caution when traveling through the project and expect lane closures and delays. This project consists of mill and inlay on various roadways throughout the Tyler District.
----------------------------------------
Cherokee County
This week, Jacksonville crews will be repairing potholes throughout the county. Rusk crews will be working on the shoulder on FM 1247. Expect daytime lane closures with flaggers controlling traffic.
Cherokee County construction projects updates:
US 84 Widening
- Limits: From 0.43 mi east of SH 110 in Rusk, northeast to the Rusk County line in Reklaw
- Contractor: Madden Contracting Company, LLC
- Cost: $7.9 million
- Anticipated Completion Date: Spring 2023
The contractor will continue placing embankment, mailboxes, and signs. The contractor is also scheduled to install final striping and rumble strips. Lane closures will be in place. Expect delays on this corridor when construction is in progress. The project will widen and resurface the roadway, along with adding safety upgrades.
FM 22 Safety Widening and Bridge Replacement Project
- Limits: From CR 1512 west of Gallatin, east to SH 110
- Contractor: Stateline Construction, LLC
- Cost: $5.5 million
- Anticipated Completion Date: Summer 2023
The contractor is scheduled to place mailboxes and signs throughout the project. Intermittent lane closures are anticipated. The project will widen the existing roadway, replace three bridges, and incorporate safety upgrades.
SH 21 Resurfacing Project
- Limits: Houston County Line east to US 69 in Alto
- Contractor: A.L. Helmcamp
- Cost: $6.0 million
- Anticipated Completion Date: Summer 2023
The contractor is scheduled to continue widening and perform base repairs as weather allows. Lane closures are anticipated. The project consists of pavement resurfacing.
SH 135 Bridge Replacements
- Limits: Mud Creek Bridge & Mud Creek Relief Bridge
- Contractor: Highway 19 Construction, LLC
- Cost: $4.2 million
- Anticipated Completion Date: Spring 2023
The contractor is scheduled to continue construction of the pavement structure on the Mud Creek and Mud Creek Relief Bridges. The road is closed to through traffic. Barricades and signage for the detour are in place. The project consists of the replacement of the bridge at Mud Creek and Mud Creek Relief.
----------------------------------------
Gregg County
Longview Maintenance will perform mobile operations to patch potholes on various roadways throughout the county. Also, crews will be working on erosion control throughout the county. Expect lane closures with flaggers controlling traffic.
Gregg County construction projects updates:
US 259 and US 80
- Limits: US 80 to James Street
- Contractor: TiZack Concrete, Inc.
- Cost: $470,000
- Anticipated Completion Date: April 2023
This project consists of installing new sidewalks and pedestrian ramps and driveways. There will be alternating lane closures, depending on which side of the roadway the contractor will be working on. Motorists are encouraged to slow down and watch for workers.
US 80 and FM 2208 (Alpine Road)
- Limits: Intersection of US 80 and FM 2208
- Contractor: Reynolds and Kay, LTD
- Cost: $784,000
- Anticipated Completion Date: April 2023
No work is scheduled this week. This project consists of installing new pedestrian signal poles, sidewalks, and handicap ramps at the intersection. There will be alternating lane closures depending on which side of the intersection they will be working on. Motorists are encouraged to slow down and watch for workers. Expect delays.
Spur 502 (Judson Road) at Eden
- Limits: Intersection of Judson Rd. and Eden Dr.
- Contractor: Reynolds and Kay, LTD
- Cost: $330,000
- Anticipated Completion Date: February 2023
No work is scheduled this week. This project consists of installing new pedestrian signal poles, sidewalks, and handicap ramps at the intersection. There will be alternating lane closures depending on which side of the intersection they will be working on. Motorists are encouraged to slow down and watch for workers. Expect delays.
SLP 281 – Sidewalk Installation
- Limits: Fairmont St. to SH 300 (Gilmer Rd.)
- Contractor: Cross Plus Construction
- Cost: $2.5 million
- Anticipated Completion Date: February 2023
This project consists of installing sidewalks on both sides of the road. There will be shoulder closures as well as some lane closures as needed. Slow down and watch for workers. Expect delays.
SH 135 – Kilgore Traffic Circle
- Limits: Traffic circle in Kilgore to Rusk County line
- Contractor: East Texas Bridge
- Cost: $8.37 million
- Anticipated Completion Date: March 2024
This project consists of completely rebuilding the traffic circle and full width of roadway to the Rusk County line. It will consist of removing existing concrete paving, reconstructing subgrade, constructing concrete paving, storm sewer installation, lighting, and striping. The traffic will be reduced to one lane in the southbound direction for the duration of the project. A detour will be set up for northbound traffic to follow SH 42. This will allow the contractor to build half of the roadway. Traffic will be switched to the newly constructed lanes later to allow completion of the other half of the highway. Expect delays.
Spur 63/McCann Road Bridge Project
- Limits: From McCann Road, north to Glencrest Lane
- Contractor: Leland Bradlee Construction
- Anticipated Completion Date: July 2023
This project is part of the City of Longview Guthrie Creek Trail project. It will consist of building a bridge over Guthrie Creek to allow bicyclist and pedestrians to travel under Spur 63. The traffic will be reduced to two lanes, one northbound lane and one south bound lane to allow the contractor to build half of the bridge. Traffic will be switched later to allow completion of the bridge construction. Expect delays.
FM 2206/Harrison Road
- Limits: Fisher Rd. to SH 42
- Contractor: East Texas Bridge, Inc.
- Cost: $14.15 million
- Anticipated Completion Date: May 2023
This project consists of widening a two-lane road to four lanes with a center turn lane. This includes drainage structures, new bridge, flexible base, hot mix, and pavement markings. Contractor will be extending culverts and constructing detours. There will be daytime lane closures. Expect delays.
FM 2206/Harrison Road
- Limits: From Loop 281 to Fisher Rd.
- Contractor: East Texas Bridge, Inc.
- Cost: $15.16 million
- Anticipated Completion Date: October 2023
This project consists of widening a two-lane road to four lanes with a center turn lane. This includes drainage structures, flexible base, curb and gutter, sidewalks, hot mix, and pavement markings. Contractor will be extending culverts and constructing detours. There will be daytime lane closures. Expect delays.
Pentecost Rd. Bridge Replacement
- Limits: US 259 Business to Stone Rd.
- Contractor: South Texas Illumination
- Cost: $638,000
- Anticipated Completion Date: March 2023
The project consists of replacing the bridge structure on Big Head Creek. Pentecost Road will be closed to through traffic. Only local traffic will be allowed. Through traffic needs to select an alternate route.
----------------------------------------
Henderson County
This week, Athens Maintenance is scheduled to perform spot seal coating on FM 753 between SH 31 and FM 2494 as well on FM 773 between SH 31 and FM 1803. A second crew will be doing edge repairs on SH 274 and SH 198. Expect lane closures with flaggers controlling traffic.
Henderson County construction projects updates:
SH 198 Bridge Project
- Limits: At the Clear Creek Bridge a mile north of FM 3054 to 0.1 mile north of CR 2830
- Contractor: Copasa Inc.
- Cost: $30.4 million
- Anticipated Completion Date: Spring 2024
The contractor is scheduled to work on the new northbound bridge and roadway elements. Motorists should be prepared for lane closures and delays. The speed limit has been reduced to 50 mph throughout the project. The project consists of the construction of replacing bridges, approaches, grading, structures, asphalt concrete pavement (ACP) base, ACP surface, retaining walls, curb & gutter, MBGF, and pavement markings.
BUS 175 Safety Improvement Project
- Limits: From BUS 19 to Grass Median 1 Mi. west of SL 7
- Contractor: Reynolds & Kay, LTD
- Cost: $700,000
- Anticipated Completion Date: Fall 2022
No work is scheduled this week. The project includes traffic signals, curb ramps and pavement markings.
SL 7 GCAA Landscape Improvement Project
- Limits: Various locations on SL 7
- Contractor: Madden Contracting Company, LLC
- Cost: $200,000
- Anticipated Completion Date: Fall 2022
No work is scheduled this week. The project includes traffic signals, curb ramps and pavement markings.
----------------------------------------
Rusk County
This week, Henderson crews will be performing bridge work at various locations throughout the county. Expect lane closures with flaggers controlling traffic. Also, a sweeper truck will be working in various locations throughout the county.
US 79 and East Main
- Limits: US 79 all four corners
- Contractor: TiZack Concrete, Inc.
- Cost: $470,000
- Anticipated Completion Date: April 2023
This project consists of installing new sidewalks and pedestrian ramps. There will be alternating lane closures, depending on which side of the roadway crews will be working on. Motorists should slow down and pay attention when traveling through the work zone.
----------------------------------------
Smith County
Tyler Maintenance will have a base failure crew on FM 16 west, before the SH 155 intersection. Expect lane closures with flaggers controlling traffic. When complete, the crew will move to FM 206 near the intersection of SP 364, to perform base repair. Expect lane closures with flaggers controlling traffic. A second crew will be performing bridge work on FM 2493 in Gresham. Expect lane closures with flaggers controlling traffic.
Smith County construction projects updates:
Sidewalks at Various Locations in Smith County
- Limits: SH 64 in Tyler (Entrada Lane to Parkdale Dr.); SH 110 in Troup (CR 2138 to FM 347); SH 135 in Troup (FM 13 to Tiger Drive)
- Contractor: Highway 19 Construction, LLC
- Cost: $3.5 million
- Anticipated Completion Date: Winter 2022
Project is in final cleanup. No work is scheduled this week. No lane closures are anticipated. The project consists of sidewalk construction along SH 64 west in Tyler, SH 110 west in Troup and SH 135 north in Troup.
FM 344, etc., Safety Improvements
- Limits: FM 344 – From FM 756 east to SH 110; FM 768 – from Loop 456, S to FM 22
- Contractor: A R Brothers Construction Services, Inc.
- Cost: $1.8 million
- Anticipated Completion Date: Spring 2023
No work is scheduled this week. Project is awaiting final punch list. The project consists of improving drainage, culvert work, and guardrail upgrades.
SH 155 Resurfacing Project
- Limits: From Loop 323 in Tyler, southwest to the Anderson County line
- Contractor: Madden Contracting Company, LLC
- Cost: $17 million
- Anticipated Completion Date: Summer 2023
The contractor is scheduled to sweep lanes out. Lane closures are anticipated. Work will be done during the day. Expect delays on this corridor when construction is in progress. The project will resurface the roadway, upgrade drainage structures, and repair bridge joints.
Tyler State Park Bridge and Resurfacing Project
- Limits: Park Maintenance Road in Tyler State Park SW to Cedar Point Camping Area Exit
- Contractor: Encino Landscape
- Cost: $2.4 Million
- Anticipated Completion Date: Summer 2023
No work is scheduled this week. The project consists of bridge and pavement resurfacing.
SH 110 & FM 346 Landscape Project
- Limits: Various locations on SH 110 & FM 346
- Contractor: Tight Line Construction, LLC
- Cost: $157,495
- Anticipated Completion Date: Winter 2022
The contractor will continue maintenance of various landscape beds. The project consists of landscape development.
Whittle Street, CR 2110, and CR 289 Bridge Replacement Project
- Limits: Whittle Street, CR 2110, CR 289
- Contractor: THK Construction, LLC
- Cost: $1.25 million
- Anticipated Completion Date: Spring 2023
No work is scheduled this week on Whittle Street at West Mud Creek Tributary. The road is closed to through traffic. The project replaces the existing bridge with a new structure.
No work is scheduled on the CR 2110 bridge at Kickapoo Creek. The road is closed to through traffic. The project replaces the existing bridge with a new structure.
No work is scheduled this week on the CR 289 bridge at Prairie Creek. The road is open to traffic. The project replaces the existing bridge with a new structure. The contractor will complete one bridge at a time.
I-20 Mill and Inlay
- Limits: Van Zandt County Line to SH 110
- Contractor: Texas Materials Group, INC.
- Cost: $6 million
- Anticipated Completion Date: Spring 2023
No work is scheduled this week. Work will resume as weather allows. Expect delays on this corridor when construction is in progress. Project consists of an overlay with TBPFC surface, ACP surface, planing, shoulder texturing and pavement markings.
US 271 Rehab, Turn Lanes, and Pavement Overlay
- Limits: From FM 16 going southwest to I-20
- Contractor: Madden Contracting Company, LLC
- Cost: $12.4 million
- Anticipated Completion Date: May 2023
No work is scheduled this week. The project consists of paving, structures, MBGF, and pavement markings from I-20 N to the Gregg County Line. The portion from IH 20 to FM 16 also includes turn lanes and pavement rehabilitation.
Safety Improvement Project (Van Zandt, Anderson, Smith, and Henderson County)
- Limits: FM 47, etc.
- Contractor: Highway 19 Construction, LLC.
- Cost: $4.5 million
- Anticipated Completion Date: Fall 2022
The contractor is scheduled to continue final cleanup on FM 346 in Smith County. Motorists should be prepared for lane closures and delays. The project includes grading, structure work, guard rail replacement and bridge rail upgrades.
SH 64 Intersection Improvement and Turn Lanes
- Limits: At CR 289 (Wolfe Lane)
- Contractor: Lonestar Equipment Co. Inc.
- Cost: $2.2 million
- Anticipated Completion Date: Fall 2023
The contractor is scheduled to continue work on drainage structures and performing ROW clearing. Expect delays on this corridor while construction is in progress. Lane closures are anticipated. Project consists of an intersection improvement and addition of turn lanes at CR 289 (Wolfe Lane).
---------------------------------------
Van Zandt County
This week, crews will be addressing high edges (moving operation) and ditch cleaning in various locations throughout the county. Expect lane closures with flaggers controlling traffic.
Van Zandt County construction projects updates:
FM 859 Safety Structures Widening
- Limits: US 80 (Edgewood) N 7 miles to SH 19
- Contractor: Baker & Company Construction, LLC.
- Cost: $3.6 million
- Anticipated Completion Date: September 2023
Crews will be extending the structure at Giladon Creek and performing right of way preparation. Two-way one lane traffic at the bridge will be managed by a 24-hour, temporary traffic signal with a contractor rep on site until approximately January 30, 2023. This safety improvement project consists of improving drainage, culverts, and bridge rail.
SH 19 Super Two Widening & Overlay (South of Canton)
- Limits: SH 243 (Canton) S 13 miles to Henderson County line
- Contractor: Big Creek Construction, LTD.
- Cost: $12.1 million
- Anticipated Completion Date: December 2023
Crews will be performing a two-inch mill and inlay at the north end of the project (Canton) and at the south end (Henderson County line) to repair pavement issues. Expect lane closures with flaggers and a pilot car controlling traffic. The project consists of super two work including grading, base repair, treated subgrade, flex base, OCST, PFC surface, structures, signs, and pavement markings.
SH 19 Super Two Widening & Overlay (North of US 80)
- Limits: US 80 N 6 miles to Rains County Line
- Contractor: A.L. Helmcamp, Inc.
- Cost: $8.8 million
- Anticipated Completion Date: December 2023
Crews will perform pavement widening operations for the northbound super two passing lane. The northbound shoulder will be closed for the duration of widening operations and will be managed by signs and channelizing devices. The project consists of super two work including grading, base repair, treated subgrade, flex base, OCST, PFC surface, structures, signs, and pavement markings.
----------------------------------------
Wood County
This week, crews are scheduled to continue edge work on FM 1647, from SH 11 to FM 852. Expect lane closures with flaggers and a pilot vehicle controlling traffic.
Wood County construction projects updates:
SH 37 Road Widening and PFC Overlay
- Limits: Quitman City Limit S 5.34 mi to 1.45 mi N of SL 564 in Mineola
- Contractor: East Texas Bridge, Inc.
- Cost: $4.58 million
- Anticipated Completion Date: May 2023
Crews will be performing bridge rail repairs and replacement at the Lake Fork Creek bridge. Traffic control will consist of a long-term shoulder closure using concrete traffic barrier (CTB) and periodic southbound lane closures managed by flaggers and a pilot vehicle. Crews will also be performing operations throughout the project including installing silt fence and rock filter dams at various locations. Motorists should expect daily lane closures with flaggers controlling traffic. The project consists of base repair, level-up, spray paver, permeable friction course surface, structures, bridge rail, metal beam guard fence, and pavement markings.
FM 2088, etc. MBGF Improvements in Wood County
· Limits: 10 locations (FM 2088, FM 17, FM 514 FM 515, FM 2966)
· Contractor: 3LW Civil, LLC
· Cost: $2.1 million
· Anticipated Completion Date: December 2022
The contractor will be addressing punch list items. Periodic, short-term lane closures may be in place at various locations. Flaggers and a pilot car will control traffic. The project is for bridge maintenance consisting of MBGF and bridge retrofit rail.
----------------------------------------
I-20 Total Maintenance Contract
- Limits: Gregg, Smith, and Van Zandt counties
- Contractor: Firemen Excavation, maintenance activities, follow up action worksheet summary for bridge work repair in Gregg, Smith, and Van Zandt Counties.
- Contractor: Andrews Diversified Industries, litter removal.
- Debris Removal/Pothole Repair Inside Lanes: Thursday through all counties; Friday after 12 p.m. emergency work only.
- Debris Removal/Pothole Repair Outside Lanes: Mon - Wed. in all counties; Friday after 12 p.m. emergency work only.
- Debris Removal/Pothole Repair Frontage Roads/Ramps: Friday in all counties
- Guardrail/Sign Repair: Emergency repairs due to vehicle crashes in all counties
- Litter Removal: Scheduled to begin I-20 removal in January 2023 in Gregg, Smith, and Van Zandt Counties. Work is also scheduled for April 2023 in Gregg County and July 2023 for all three counties.
- Delineation/Reflectors: Work will continue in Gregg, Smith, and Van Zandt Counties.
Copyright 2022 KLTV/KTRE. All rights reserved.