Roadwork in East Texas for the week of May 29

(Source: KLTV staff)
Published: May. 30, 2023 at 5:52 AM CDT
Email This Link
Share on Pinterest
Share on LinkedIn

Relased by the Texas Department of Transportation:

EAST TEXAS (Press Release) - TxDOT is planning to conduct the following construction and maintenance work in the district during the week of May 29, 2023. Work schedules are subject to change due to weather conditions, equipment failure, or other unforeseen issues. Please slow down and pay attention in work zones.

Anderson County

Palestine Maintenance will be blading level ups and patches on FM 321 in Tennessee Colony. Expect lane closures with flaggers controlling traffic.

Anderson County construction projects updates:

US 175 Widening Project

  • Limits: From 0.4 miles SE of SH 155, SE to Cuney
  • Contractor: Big Creek Construction, LTD
  • Cost: $55.5 million
  • Anticipated Completion Date: Spring 2026

The contractor is scheduled to work on the new eastbound bridge and roadway elements. The speed limit is reduced throughout the project limits. Motorists should use caution when traveling through the project and expect lane closures and delays. Project consists of expansion to a four-lane roadway with new bridges across the Neches River.

SH 155 Overlay Project

  • Limits: From 0.14 Mi S of FM 19 (End of Curb and Gutter) to S of FM 315
  • Contractor: Madden Contracting Company, LLC
  • Cost: $14.6 million
  • Anticipated Completion Date: Summer 2023

Weather permitting, the contractor is scheduled to continue working on drainage structures. The speed limit has been reduced to 60 mph throughout the project. Motorists should use caution when traveling through the project and expect lane closures and delays. The project consists of one course surface treatment (OCST), permeable friction course (PFC) surface, shoulder texturing, edge treatment and pavement markings.

Gus Engeling Park Project

  • Limits: Various locations in Gus Engeling WMA
  • Contractor: Baker & Company Construction, LLC
  • Cost: $0.9 million
  • Anticipated Completion Date: Summer 2023

The contractor is scheduled to work on drainage elements and begin seal coat operations. Motorists should use caution when traveling through the project and expect lane closures and delays. It consists of base overlay and drainage improvements.

----------------------------------------

Cherokee County

Jacksonville crews will be performing bridge maintenance at various locations throughout the county. Expect lane closures with traffic controlled by flaggers. Rusk maintenance will continue widening FM 768 between Loop 456 and FM 22. Expect daytime lane closures with traffic controlled by flaggers.

Cherokee County construction projects updates:

US 84 Widening

  • Limits: From 0.43 mi east of SH 110 in Rusk, northeast to the Rusk County line in Reklaw
  • Contractor: Madden Contracting Company, LLC
  • Cost: $7.9 million
  • Anticipated Completion Date: Spring 2023

The project is in suspension and pending punch list inspection. There will be no lane closures in place. The project will widen and resurface the roadway, along with adding safety upgrades.

FM 22 Safety Widening and Bridge Replacement Project

  • Limits: From CR 1512 west of Gallatin, east to SH 110
  • Contractor: Stateline Construction, LLC
  • Cost: $5.5 million
  • Anticipated Completion Date: Summer 2023

The project is in suspension and pending punch list inspection. No work will be done in the upcoming weeks. The project widens the existing roadway, replace three bridges, and incorporate safety upgrades.

SH 21 Resurfacing Project

  • Limits: Houston County Line east to US 69 in Alto
  • Contractor: A.L. Helmcamp
  • Cost: $6.0 million
  • Anticipated Completion Date: Summer 2023

The contractor will not be doing any production related work until the start of seal coat season in May. Equipment has been demobilized. The project will consist of pavement resurfacing.

SH 135 Bridge Replacements

  • Limits: Mud Creek Bridge & Mud Creek Relief Bridge
  • Contractor: Highway 19 Construction, LLC
  • Cost: $4.2 million
  • Anticipated Completion Date: Spring 2023

The contractor has completed all operations on SH 135 and the road is now open. The project is awaiting removal of RFDs and silt fence upon vegetative erosion control growth. The project consists of the replacement of the bridge at Mud Creek and Mud Creek Relief.

SH 294 Rehabilitation Project

  • Limits: From CR 2326, E to SH 21
  • Contractor: Madden Contracting Company LLC
  • Cost: $3.4 million
  • Anticipated Completion Date: Fall 2023

The contractor will begin installing driveway pipes, safety end treatments. No lane closures are anticipated. The project consists of pavement resurfacing.

District Mill and Inlay Project

  • Limits: US 287, etc.
  • Contractor: Big Creek Construction, LTD
  • Cost: $0.8 million
  • Anticipated Completion Date: Summer 2023

Mill and inlay work is scheduled to begin on SL 456 in Jacksonville. Work is scheduled to be completed at night. Motorists should expect lane closures to begin at 7 p.m., Sunday through Thursday nights. Motorists should use caution when traveling through the project and expect lane closures and delays. This project consists of mill and inlay on various roadways throughout the Tyler District.

----------------------------------------

Gregg County

Longview Maintenance will be performing mechanical sweeping operations on various roadways throughout the county. Crews will also continue edge preparation on FM 1639. Both are mobile operations.

Gregg County construction projects updates:

US 80 and FM 2208 (Alpine Road)

  • Limits: Intersection of US 80 and FM 2208
  • Contractor: Reynolds and Kay, LTD
  • Cost: $784,000
  • Anticipated Completion Date: May 2023

This project consists of installing new pedestrian signal poles, sidewalks, and handicap ramps at the intersection. Expect lane closures and workers present.

Spur 502 (Judson Road) at Eden

  • Limits: Intersection of Judson Rd. and Eden Dr.
  • Contractor: Reynolds and Kay, LTD
  • Cost: $330,000
  • Anticipated Completion Date: June 2023

This project consists of installing new traffic signal, sidewalks, and handicap ramps at the intersection.  Expect lane closures and workers present.

SLP 281, SH 300 and Estes Parkway

  • Limits: For SLP 281 - Fairmont St. to SH 300 (Gilmer Rd.); SH 300 – Reel Rd. to Evergreen St.; Estes Pkwy – Walmart north to I-20
  • Contractor: Cross Plus Construction
  • Cost: $2.5 million
  • Anticipated Completion Date: June 2023

This project consists of installing sidewalks on both sides of the road. There will be shoulder closures as well as some lane closures as needed.  Slow down and watch for workers. Expect delays.

SH 135 – Kilgore Traffic Circle

  • Limits: Traffic circle in Kilgore to Rusk County line
  • Contractor: East Texas Bridge
  • Cost: $8.37 million
  • Anticipated Completion Date: March 2024

This project consists of completely rebuilding the traffic circle and full width of roadway to the Rusk County line. It will consist of removing existing concrete paving, reconstructing subgrade, constructing concrete paving, storm sewer installation, lighting, and striping. The traffic will be reduced to one lane in the southbound direction for the duration of the project. A detour will be set up for northbound traffic to follow SH 42. This will allow the contractor to build half of the roadway. Traffic will be switched to the newly constructed lanes later to allow completion of the other half of the highway. Expect delays.

FM 2206/Harrison Road

  • Limits: Fisher Rd. to SH 42
  • Contractor: East Texas Bridge, Inc.
  • Cost: $14.15 million
  • Anticipated Completion Date: May 2023

This project consists of widening a two-lane road to four lanes with a center turn lane. This includes drainage structures, new bridge, flexible base, hot mix, and pavement markings. Contractor will be extending culverts and constructing detours. There will be daytime lane closures. Expect delays.

FM 2206/Harrison Road

  • Limits: From Loop 281 to Fisher Rd.
  • Contractor: East Texas Bridge, Inc.
  • Cost: $15.16 million
  • Anticipated Completion Date: October 2023

This project consists of widening a two-lane road to four lanes with a center turn lane.  This includes drainage structures, flexible base, curb and gutter, sidewalks, hot mix, and pavement markings.  Contractor will be extending culverts and constructing detours.  There will be daytime lane closures.  Expect delays.

High St. Bridge over UP Railroad

  • Limits: Nelson St. to Marion Dr.
  • Contractor: Ragle Construction
  • Cost: $9.3 million
  • Anticipated Completion Date: January 2025

The project consists of replacing the High Street bridge structure over the UP railroad. High Street will be reduced to two lanes – one northbound lane and one southbound lane. One half of the bridge will be constructed at a time.  Expect delays. Traffic may want to seek alternate routes.

US 80 - Gladewater

  • Limits: SH 300 east to Locker Plant Road in Gladewater
  • Contractor: East Texas Bridge
  • Cost: $12.6 million
  • Anticipated Completion Date: November 2023

This project consists of milling and inlaying main lanes of travel, as well as striping. There will be daytime lane closures. Motorists should expect delays.

US 80 – Pedestrian Safety Improvements

  • Limits: East of Alpine Road (FM 2208)
  • Contractor: Encino Landscape
  • Cost: $548,000 for numerous locations throughout the district
  • Anticipated Completion Date: May 2023

This project consists of installing new pedestrian sidewalks and handicap ramps near the intersection. Motorists should expect daytime lane closures and delays.

US 259 Bypass in Kilgore

  • Limits: SH 31 to the Rusk County line
  • Contractor: Madden Construction
  • Cost: $4.5 million
  • Anticipated Completion Date: June 2023

This project consists of milling and inlaying hot mix asphalt on all lanes and restriping. There will be alternating lane closures. Slow down and watch for workers. Expect delays.

US 259 North

  • Limits: FM 1844 to Upshur County line
  • Contractor: Madden Construction
  • Cost: $5.03 million
  • Anticipated Completion Date: June 2023

This project consists of milling base repairs and overlaying hot mix asphalt on all lanes, and restriping. There will be alternating lane closures. Slow down and watch for workers. Expect delays.

----------------------------------------

Henderson County

Athens Maintenance is scheduled to perform base failure repair and edge repair on various roadways throughout the county, including FM 2709. Expect lane closures with flaggers controlling traffic. Also, crews will be performing edge repair and ditch maintenance on various roadways throughout the county. Expect lane closures with flaggers controlling traffic.

Henderson County construction projects updates:

SH 198 Bridge Project

  • Limits: At the Clear Creek Bridge a mile north of FM 3054 to 0.1 mile north of CR 2830
  • Contractor: Copasa Inc.
  • Cost: $30.4 million
  • Anticipated Completion Date: Spring 2024

The contractor is scheduled to work on demolition of the existing bridge and placement of drilled shafts for the new bridge. Motorists should be prepared for lane closures and delays. The speed limit has been reduced to 50 mph throughout the project. The project consists of the construction of replacing bridges, approaches, grading, structures, ACP base, ACP surface, retaining walls, curb & gutter, MBGF, and pavement markings.

BUS 175 Safety Improvement Project

  • Limits: From BUS 19 to Grass Median 1 Mi. west of SL 7
  • Contractor: Reynolds & Kay, LTD
  • Cost: $700,000
  • Anticipated Completion Date: Summer 2023

The contractor is scheduled to begin seal coat operations. The project includes traffic signals, curb ramps and pavement markings.

SL 7 GCAA Landscape Improvement Project

  • Limits: Various locations on SL 7
  • Contractor: Tight Line Construction, LLC
  • Cost: $0.2 million
  • Anticipated Completion Date: Spring 2023

No work is scheduled. The project includes traffic signals, curb ramps, and pavement markings.

BUS 31 Sidewalk Project

  • Limits: From Carroll St to Flat Creek Rd
  • Contractor: Highway 19 Construction, LLC
  • Cost: $2.3 million
  • Anticipated Completion Date: Fall 2023

The contractor is scheduled to continue working on the eastbound sidewalk over the railroad bridge and other location along BUS 31. Motorists should be prepared for lane closures and delays. The project includes pavement structure repairs, sidewalks, pavement markings and signage.

FM 316 Rehabilitation

  • Limits: From FM 1861 to US 175
  • Contractor: Baker & Company Construction, LLC
  • Cost: $7.9 million
  • Anticipated Completion Date: Spring 2024

The contractor is scheduled to continue removing and trimming trees. Motorists should use caution when traveling through the project and expect lane closures with delays. The project includes pavement reconstruction, structures, pavement markings and signs.

----------------------------------------

Rusk County

Henderson Maintenance will have a crew digging ditches on various roadways throughout the county. A second crew will be patching on various roadways throughout the county. Expect daytime lane closures and flaggers controlling traffic.

Rusk County construction projects updates:

SH 64 and Mill Street Intersection/US 79 and Webster Street

  • Limits: Intersection
  • Contractor: Reynolds and Kay, LTD
  • Cost: $784,000
  • Anticipated Completion Date: May 2023

This project consists of installing new pedestrian signal poles, sidewalks, and handicap ramps at the intersection. There will be daytime lane closures. Motorists should expect delays.

US 84

  • Limits: FM 225 west to the county line
  • Contractor: Madden Construction
  • Cost: $2.4 Million
  • Anticipated Completion Date: October 2023

This project consists of reconstructing and widening US 84, extended culverts, and new striping. There will be daytime lane closures. Motorists should expect delays.

----------------------------------------

Smith County

Tyler Maintenance will have a ditch crew on FM 2015, just north of I-20. This will be under flagging operations. Once complete, this crew will move to SH 64 at CR 1147 to fix a washout in the right-of-way. They will then move to FM 2710 to fix washout in the right-of-way, just west of FM 14. Both locations will be under flagging operations. A second crew will be performing bridge work on Barber Rd. at I-20. This will be under flagging operation. Once complete, this crew will move to Broadway Ave. inside Loop 323 near Discount Tire. This project will be working off the roadway. They will then move to SH 64 at the SH 135 overpass. Expect lane closures with flaggers controlling traffic. There will also be a sweeper unit at various locations throughout the county.

Smith County construction projects updates:

Sidewalks at Various Locations in Smith County

  • Limits: SH 64 in Tyler (Entrada Lane to Parkdale Dr.); SH 110 in Troup (CR 2138 to FM 347); SH 135 in Troup (FM 13 to Tiger Drive)
  • Contractor: Highway 19 Construction, LLC
  • Cost: $3.5 million
  • Anticipated Completion Date: Winter 2022

Project is in final cleanup. No work is scheduled this week. No lane closures are anticipated. The project consists of sidewalk construction along SH 64 west in Tyler, SH 110 west in Troup and SH 135 north in Troup.

FM 344, ETC. Safety Improvements

  • Limits: FM 344 – From FM 756, E to SH 110; FM 768 – From SL 456, S to FM 22
  • Contractor: A R Brothers Construction Services, Inc.
  • Cost: $1.8 million
  • Anticipated Completion Date: Spring 2023

No work is scheduled this week. Project is awaiting final punch list. The project consists of improving drainage, culvert work, and guard rail upgrades.

SH 155 Resurfacing Project

  • Limits: From Loop 323 in Tyler, southwest to the Anderson County line
  • Contractor: Madden Contracting Company, LLC
  • Cost: $17 million
  • Anticipated Completion Date: Summer 2023

The contractor is scheduled to begin laying PFC surface to the shoulders and will be conducting work at the turn lane at FM 2868. Expect delays and lane closures on this corridor when construction in in progress. The work is scheduled to be completed during the day and night. The project consists of resurfacing the roadway, upgrading drainage structures, and repairing bridge joints.

Tyler State Park Bridge and Resurfacing Project

  • Limits: Park Maintenance Road in Tyler State Park SW to Cedar Point Camping Area Exit
  • Contractor: Encino Landscape
  • Cost: $2.4 Million
  • Anticipated Completion Date: Summer 2023

The project is no longer under time suspension and contractor is expecting to resume work soon. The project consists of bridge and pavement resurfacing.

Tyler State Park Rehabilitation Project

  • Limits: Park Maintenance roads, camp areas 5-8, additional parking in camp area 10, day use parking area curb and gutter repair
  • Contractor: East Texas Bridge, Inc.
  • Cost: $851,000
  • Anticipated Completion Date: Summer 2023

The contractor is scheduled to conduct hot mix placement on Milestone 4 (Area 10 Creekside Camping) location. Park areas will be closed as operations are in progress. This project is the rehabilitation of parking areas at camp site and maintenance roadways.

SH 110 & FM 346 Landscape Project

  • Limits: Various locations on SH 110 & FM 346
  • Contractor: Tight Line Construction, LLC
  • Cost: $157,495
  • Anticipated Completion Date: Winter 2022

The project is suspended and awaiting punch list inspection for the Whitehouse landscape project. The project consists of landscape development.

Whittle Street, CR 2110, and CR 289 Bridge Replacement Project

  • Limits: Whittle Street, CR 2110, CR 289
  • Contractor: THK Construction, LLC
  • Cost: $1.25 million
  • Anticipated Completion Date: Spring 2023

No work is scheduled this week on Whittle Street at West Mud Creek Tributary. The project is in suspension and pending change order operations at the Whittle Street Bridge site. The road is open to through traffic. The project consists of replacing the existing bridge with a new structure.

No work is scheduled on the CR 2110 bridge at Kickapoo Creek. The road is open to through traffic. The project replaces the existing bridge with a new structure.

No work is scheduled this week on the CR 289 bridge at Prairie Creek. The road is open to traffic. The project replaces the existing bridge with a new structure. The contractor will complete one bridge at a time.

I-20 Mill and Inlay

  • Limits: Van Zandt County Line to SH 110
  • Contractor: Texas Materials Group, INC.
  • Cost: $6 million
  • Anticipated Completion Date: Spring 2023

No work is scheduled this week. The project is in time suspension. Expect delays on this corridor when construction is in progress. Project consists of an overlay with TBPFC surface, ACP surface, planing, shoulder texturing and pavement markings.

US 271 Rehab, Turn Lanes, and Pavement Overlay

  • Limits: From FM 16 going southwest to I-20
  • Contractor: Madden Contracting Company, LLC
  • Cost: $12.4 million
  • Anticipated Completion Date: October 2023

The project consists of paving, structures, MBGF, and pavement markings from IH 20 N to the Gregg County Line. The portion from IH 20 to FM 16 also includes turn lanes and pavement rehabilitation. The southbound outside lane and shoulder are closed indefinitely while rehab work is ongoing and will be managed by signs channelizing devices.  No additional lane closures are anticipated. Crews have started laying hot mix in the southbound outside lane. Motorists should drive with caution and expect delays.

SH 64 Intersection Improvement and Turn Lanes

  • Limits: At CR 289 (Wolfe Lane)
  • Contractor: Lonestar Equipment Co. Inc.
  • Cost: $2.2 million
  • Anticipated Completion Date: Fall 2023

Weather permitting, the contractor is scheduled to widen areas and place hot mix and possible seal coat. Weather permitting, contractor could begin laying hot mix. Expect delays on this corridor while construction is in progress. Lane closures are anticipated. Project consists of an intersection improvement and addition of turn lanes at CR 289 (Wolfe Lane).

FM 16 Widening and Realignment

· Limits: 4 mi west of FM 849 east to US 69 in Lindale

· Contractor: Highway 19 Construction LLC.

· Cost: $44.4 million

· Anticipated Completion Date: August 2025

The project consists of grading, asphalt base, asphalt surface overlay paving, storm drain, bridge, and culvert structures, signing, pavement markings, and signals. Crews will be preparing the right-of-way by removing trees and grading embankment. There will be a crew working to install a detour for a traffic switch near Lindale Cemetery Road. Lane closures will be present in the area. Motorists should drive with caution and expect delays.

US 69 Rehab Existing Road and Restricted Crossing U-Turn (R-Cut)

  • Limits: Cumberland Road to .308 miles south of FM 2813
  • Contractor: Drewery Construction Company, INC
  • Cost: $7.8 million
  • Anticipated Completion Date: Fall 2023

No work is scheduled this week. This project consists of rehabilitating existing roadway and installing a restricted crossing U-turn (R-Cut) at FM 2813 intersection.

SL 323 Overlay on Existing Roadway

  • Limits: .3 mi N of SH31, Elm St in W Tyler, N to .25 mi E of US69
  • Contractor: Drewery Construction Company, INC
  • Cost: $4.5 million
  • Anticipated Completion Date: Fall 2023

The Contactor is scheduled to place barricades and signage within the limits of the project. Expect lane closures and delay in travel. This project consists of overlaying existing roadway with PFC asphalt.

SH 110 in Whitehouse

  • Limits: Whitehouse
  • Contractor: Cross Plus Construction
  • Cost: $2.5 million
  • Anticipated Completion Date: July 2023

This project consists of installing sidewalks. There will be shoulder closures along with some lane closures as needed. Slow down and watch for workers. Expect delays.

---------------------------------------

Van Zandt County

Canton Maintenance will have a crew performing base repairs on FM 90. A second crew will be patching at various locations throughout the county.

Van Zandt County construction projects updates:

FM 859 Safety Structures Widening

  • Limits: US 80 (Edgewood) N 7 miles to SH 19
  • Contractor: Baker & Company Construction, LLC.
  • Cost: $3.6 million
  • Anticipated Completion Date: September 2023

This safety improvements project consists of improving drainage, culverts, and bridge rail. Crews will be working behind the guardrail and bridge rail at the other bridge near FM 1395 over Giladon Creek Branch. Crews will be installing driveway culverts. Lane closures are expected, and motorist should expect delays.

SH 19 Super Two Widening & Overlay (South of Canton)

  • Limits: SH 243 (Canton) S 13 miles to Henderson County line
  • Contractor: Big Creek Construction, LTD.
  • Cost: $12.1 million
  • Anticipated Completion Date: June 2023

The contractor will be installing signs and pavement markings. Lane closures are anticipated. The project consists of super two work including grading, base repair, treated subgrade, flex base, OCST, PFC surface, structures, signs, and pavement markings.

SH 19 Super Two Widening & Overlay (North of US 80)

  • Limits: US 80 N 6 miles to Rains County Line
  • Contractor: A.L. Helmcamp, Inc.
  • Cost: $8.8 million
  • Anticipated Completion Date: December 2023

The project consists of Super 2 type work, including grading, base repair, treated subgrade, flex base, OCST, PFC surface, structures, signs, and pavement markings. There is a reduced speed limit of 55 mph through the project. The northbound shoulder will be closed for the duration of widening operations and will be managed by signs and channelizing devices. Crews are working to install embankment, flex base, and hot mix inside the shoulder closure area. Lane closures are expected, and motorists should expect delays.

US 80 – Wills Point

  • Limits: Intersection of US 80 and SH 64
  • Contractor: Encino Landscape
  • Cost: $548,000 for numerous locations
  • Anticipated Completion Date: May 2023

This project consists of installing new pedestrian sidewalks and handicap ramps near the intersection. The majority of the work has been completed, but illumination still needs to be installed. Daytime lane closures could exist. Motorists should expect delays. Please watch for pedestrians crossing the roadway.

CR 2112 Bridge Replacement

  • Limits: Bridge at Caney Creek
  • Contractor: THK Construction, LLC
  • Cost: $521,961.28
  • Anticipated Completion Date: July 2023

This project is for the construction of a bridge replacement, consisting of replacing bridge and approaches, grading, ACP base, and surface, and metal beam guard fence installation. Work is scheduled to begin in May. The road will be closed until project completion in July. Motorists should seek alternate routes for the duration of the project.

I-20 Frontage Roads West of FM 314 and East of FM 47

  • Limits: FM 314 west one mile and FM 47 to CR 3416
  • Contractor: H.V. Caver, Inc.
  • Cost: $5.7 Million
  • Anticipated Completion Date: December 2023

This project is for the construction of roadway restoration consisting of scarifying, treating existing material & subgrade, flex base, prime coat, TCST, ACP base, ACP surface, metal beam guard fence, structures, signs, and pavement markings. Work will be starting in mid-June due to material delays and the frontage roads will be closed, one at a time, until roadway work is completed. Motorists should prepare for delays and seek alternate routes for the duration of the project.

----------------------------------------

Wood County

This week, crews are scheduled to blade overlay on FM 3056 from US 80 to FM 778. Expect lane closures with flaggers and a pilot car controlling traffic.

Wood County construction projects updates:

SH 37 Road Widening and PFC Overlay

  • Limits: Quitman City Limit S 5.34 mi to 1.45 mi N of SL 564 in Mineola
  • Contractor: East Texas Bridge, Inc.
  • Cost: $4.58 million
  • Anticipated Completion Date: June 2023

The project consists of base repair, level-up, spray paver, permeable friction course surface, structures, bridge rail, metal beam guard fence, and pavement markings. Crews will be placing ACP driveways. The PFC surface operations are projected to begin at the end of May. Lane closures may be possible during the driveway installations and are expected during the PFC installation.

SH 37 – Quitman

  • Limits: Intersection near Red Bud Lane
  • Contractor: Encino Landscape
  • Cost: $548,000
  • Anticipated Completion Date: May 2023

This project consists of installing new pedestrian signal poles, sidewalks, and handicap ramps at the intersection. Daytime lane closures could exist. Motorists should expect delays.

FM 14

  • Limits: From FM 2869 to East of FM 1795
  • Contractor: East Texas Bridge, Inc.
  • Cost: $2.6 Million
  • Anticipated Completion Date: July 2023

This project is for the construction of safety improvements, consisting of PFC surface overlay, culvert work, safety end treatments, rumble strips, and pavement markings. There will be daytime lane closures. Motorists should expect delays. Crews are currently working on driveways.

FM 1804 Bridge Replacement

  • Limits: Bridge at Black Creek
  • Contractor: THK Construction, LLC
  • Cost: $634,567
  • Anticipated Completion Date: July 2023

This project is for the construction of a bridge-class culvert consisting of the removal of the existing bridge and approaches, a new bridge-class culvert, roadway approaches, grading, ACP base and surface, and metal beam guard fence installation. Work is scheduled to begin in May. The road will be closed until project completion in July. Motorists should seek alternate routes for the duration of the project.

----------------------------------------

I-20 Total Maintenance Contract

  • Limits: Gregg, Smith, and Van Zandt counties
  • Contractor: Firemen Excavation, maintenance activities, follow up action worksheet summary for bridge work repair in Gregg, Smith, and Van Zandt Counties.
  • Contractor: Andrews Diversified Industries, litter removal.
  • Debris Removal/Pothole Repair Inside Lanes: No work scheduled due to the holiday.
  • Debris Removal/Pothole Repair Outside Lanes: No work scheduled due to the holiday.
  • Debris Removal/Pothole Repair Frontage Roads/Ramps: Friday in all counties
  • Guardrail/Sign Repair: Emergency repairs due to vehicle crashes in all counties
  • Litter Removal: Work is scheduled for April 2023 in Gregg County and July 2023 for Gregg, Smith, and Van Zandt Counties.
  • Delineation/Reflectors: Work will continue in Gregg, Smith, and Van Zandt Counties.
  • Tree Removal: Gregg, Smith, and Van Zandt Counties.
  • Raised Pavement Markers: Night work will be done from 8 p.m. to 5 a.m. daily in Gregg, Smith, and Van Zandt Counties.